01Should I go with the cheapest quote?+
With the genuinely cheapest one, which you only know once the bids answer the same basis. A low total with long exclusions or short measurements usually ends up costing more than a complete bid.
02What are exclusions and why do they matter so much?+
They are the works and costs a bid does not include: from permits and fees to rubble removal or final cleaning. What is excluded is paid later, at prices no longer negotiated. That is why every company is asked for the same list of exclusions.
03How do I stop extras from inflating the price?+
By asking for unit prices in the bid and fixing in the contract that extras are valued at those same rates. During the works, each change is documented with its reason, scope and impact before it is carried out, so you decide with the figure in front of you.
04Can I compare a general contractor’s quote with bids from trades?+
Yes, if both are broken down by line item. The contractor’s price includes its margin, typically 15–25% of the construction cost; trade bids are added up package by package plus the fixed management fee, from €8,000 with Luthier Split. The comparison also has to include who coordinates and who answers for the interfaces between trades.
05How do you make bids comparable?+
We establish a common scope and requirements, then review items, specifications, exclusions and timing to explain the differences before you decide.
06Can you join when the design is complete?+
Yes. We review what needs clarification before tendering: scope, quantities, specifications, trade interfaces and schedule. The proposal reflects the actual project stage.