Gaps in the design
What the design does not say, the site decides. An undetailed junction, an unspecified finish or a short measurement becomes an extra as soon as someone has to build it.
Guide / Changes and overruns
Almost no build finishes on the budget it started with. What separates a controlled project from one that runs away is not the absence of changes, but that every change is known, priced and decided before it is carried out, and that the money committed is known at all times.
Luthier · Project ManagementUpdated October 2026.
01 / Where it comes from
There is rarely a single culprit. The usual story is a string of small decisions taken in a hurry, without a figure on the table.
What the design does not say, the site decides. An undetailed junction, an unspecified finish or a short measurement becomes an extra as soon as someone has to build it.
Changing a layout, a window or a finish mid-build is legitimate. The problem is doing it without knowing what it costs and what it delays, and finding out on the next invoice.
What appears when you open up: a damaged beam, a service that was not on the drawings, ground that differs from the survey. They cannot be avoided, but they are priced like any other change.
Work carried out without an agreed price is paid at whatever price the person who did it names. Without unit rates in the quote, there is nothing to argue with.
Large deposits and unchecked payment applications let the money leave before the work is done. By the time the deviation is spotted, it has already been paid.
02 / The process
A change is any work that was not in the contract or that is done differently, whether the owner asks for it, the architect proposes it or the contractor discovers it. All of them follow the same route.
Whoever spots it describes it in writing: what changes, why, and against which item in the contract. Nothing is carried out at this stage.
The trade or the contractor is asked for the price, using the unit rates in their quote, and for the effect on the schedule. We check that what has been priced is exactly what was proposed.
You approve or reject it with the figure, the time and the alternatives in front of you. The decision is recorded with its date.
The approved change goes into the contract budget and the programme. Only then is it carried out, and only then can it be certified.
When a change cannot wait, a cost cap and a date for the final price are fixed in writing. What is not accepted is carrying out the work and asking the price afterwards.
03 / The money
Control is not reading invoices: it is knowing at any moment how much is contracted, how much has been done, how much has been paid and how much sits in changes still to be decided.
The reference budget is still the original quote, even after changes have been approved.
Payment applications are paid as they arrive, without checking progress on site.
Extras turn up bundled in the final invoice.
Nobody knows how much is left to pay until the end.
A contract budget updated with every approved change.
Payment applications checked against real progress before payment is approved.
Every change with its status: proposed, priced, approved or rejected, incorporated.
A table of where every euro goes: contracted, done, paid and outstanding, by package.
A retention held until handover.
04 / The contract
The quote is contracted with its prices per unit. Extras are priced with those same rates, not with new ones.
No work outside the contract is carried out without a change order approved in writing. It is agreed who requests it, who prices it and within how many days.
Periodic payment applications for work done and measured, with a retention for defects. Deposits only for specific, justified materials.
A schedule by phases and the rule for revising it when an approved change alters it.
05 / The signs
Deviations give warning before they appear on an invoice. These are the signs we look at every week.
Work under way that is not covered by any change order.
Payment applications rising faster than the progress visible on site.
Answers like “we already discussed that”, with nothing in writing.
A list of extras that keeps growing and is never priced.
Decisions asked of you on site, standing up, for today.
Every change has a document with its figure and the date it was decided.
You know how much you have committed and how much is left, not just how much you have paid.
Payment applications are approved after being checked, not before.
Decisions reach you with alternatives and with time to think.
The contract budget and the programme are up to date.
With a general contractor or with direct trades the route is the same. What changes is who prices the work: the contractor in one case, each trade in the other. How to choose between the two models is covered in another guide. Read the guide
06 / What it costs
Change control, checking payment applications and tracking the budget are part of Luthier Build, during construction. If the work is contracted trade by trade, control runs package by package and starts in Luthier Split, with the contracts.
Fees are fixed and agreed in the proposal. We do not take a percentage of the construction cost or of the companies carrying it out: when a change is priced, we have no interest in it going up.
PEM: direct construction cost (Presupuesto de Ejecución Material).
07 / FAQ
Answers to help you make an informed decision before starting.
Changes are common: gaps in the design, owner decisions or what appears when you open up. What is not normal is learning their cost once they have been carried out. A controlled build has changes too; the difference is that each one was decided with the figure on the table.
In Spain it is the agreed price for work that was not in the contract, settled between the parties before the work is done. It is built from the unit rates in the quote or, where none exist, from justified prices. It is the document that turns an extra into an approved change.
A cost cap and a date for the final price are fixed in writing, and the work goes ahead on that condition. What is not accepted is carrying out work without an order and asking the price afterwards.
It is the measurement of the work done in a period, valued at the contract prices, which triggers payment. It is checked by comparing what is claimed with what is on site, because paying ahead of progress is the quietest way to lose control.
The architect and the site direction judge whether a change is technically sound. The financial decision is the owner’s, because it is your money. Our job is to get it to you with the scope, the figure and the schedule clear before anything is carried out.
We document the proposed change, its reason and known cost and time impact. We review it with the relevant parties and record the client’s decision before incorporating it into the scope.
We can assess joining a live project after reviewing its condition, contracts, documents and outstanding decisions, then define what monitoring we can take on and from when.