Projects / Residential building

Extension of a listed buildingSant Gervasi, Barcelona

Project run by the Luthier team · 2022–2024

Construction budget
≈ 560,000 €
Floor area
≈ 361 m²
Period
2022–2024
Elevated view of the complete steel structure of the extension between party walls

01 / What it was

Extension of a listed apartment building onto the neighbouring plot, with four new flats, a commercial unit and parking: micropile foundations, steel structure with composite floor slabs and intumescent fire protection, lime-mortar rendered façade with silicate paint, individual aerothermal heat pumps, thermally broken joinery and parquet flooring.

02 / What the project demanded

Extending a listed building onto the neighbouring plot, with micropiles and a steel structure that on site called for more steel than budgeted. The party walls forced a rethink of the planned enclosure, with hacking-off, dry linings and external insulation against the adjoining building, and modifications to the existing balconies. Every change was priced as a variation and the measurements were reconciled with the client item by item.

03 / What we apply today

Between party walls, what shapes the works is the neighbours: their structure, their courtyards, their timescales. In Luthier Plan the surroundings are studied in the same detail as the building itself, before tenders are invited.

Tell us about your project

04 / Technical data

Programme
Extension of a listed apartment building onto the neighbouring plot: 4 new flats, enlargement of the commercial units and parking on the ground floor; the resulting building has 9 flats, 2 commercial units and parking
Built area
≈ 361 m²
Storeys
GF+2 and flat roof; no basement
Construction budget (excl. VAT)
≈ 560,000 €
Construction period
22 months
Structure
Foundations of 150 mm self-drilling micropiles and pile caps; steel structure of rolled sections with 15 cm composite floor slab on profiled steel decking and shear studs
Envelope
14 cm brick masonry façade with rock wool insulation and plasterboard dry lining, finished with lime mortar render and silicate paint
Building services
Individual aerothermal heat pump per flat, ducted air conditioning, rooftop solar thermal for domestic hot water as per design, timed extractor fans in bathrooms, electrical and plumbing installations
Parties coordinated
Site direction team (architect and technical architect), structural engineer and 21 trades and suppliers, one per trade

05 / Images

Let's talk.

A first conversation, with no strings, to understand your project.

Or reach us directly:
hola@luthier.pm
Your data stays with us. We only use it to reply to you.

Your data stays with us. We only use it to reply to you.